Skip to main content
How-To · 14 min read

PLI Solar Tranche-II SECI 39,600 MW 11-Bidder Reconciliation

Under the MNRE PLI High Efficiency Solar PV Modules scheme, Tranche-II Rs 19,500 crore was implemented by the Solar Energy Corporation of India (SECI) with Letters of Award issued in April 2023 for 39,600 MW of integrated manufacturing capacity across 11 selected bidders. Each awardee — from Waaree Energies with 6,000 MW down to First Solar Manufacturing with 600 MW — runs a per-bidder commissioning tracker across the Year 1 pilot through Year 5 full commercial capacity window, a per-MW incentive computation against the Rs 4,000 to 6,000 per kW indicative band, a Y-o-Y DVA achievement register, and the SECI portal milestone reporting cycle with facility-commissioning-penalty exposure if applicable.

Terra Insight
Terra Insight Editorial Team Reconciliation Infrastructure

Content authored by practitioners with experience at Amazon India, Intuit QuickBooks, and the Tata Group. Meet the team →

Published 22 July 2026
Domain expertise
TDS Reconciliation GST Input Credit Platform Settlements NACH Batch Matching Bank Reconciliation Form 26AS Matching ERP Integrations Enterprise Finance Ops
Knowledge Card
Problem

Each of the 11 SECI Tranche-II Letter of Award holders across the 39,600 MW awarded April 2023 under the MNRE PLI Solar PV Modules Rs 19,500 crore leg — from Waaree Energies at 6,000 MW through First Solar Manufacturing at 600 MW — must reconcile a per-bidder commissioning tracker across the Year 1 pilot (typically 5 percent of awarded capacity) through Year 5 full commercial capacity (100 percent) window, a per-MW incentive computation against the Rs 4,000 to Rs 6,000 per kW illustrative Tranche-II indicative band bound by the LoA ceiling, a Y-o-Y DVA achievement register against the scheme floor for each year (integrated line typically Y1 20 to 25 percent scaling to Y5 40 to 45 percent), the SECI portal milestone reporting cycle with third-party inspection agency (TPIA) certifications and Bureau of Indian Standards module-testing lab reports, a facility commissioning penalty exposure register for any shortfall against the year's target subject to force majeure exception review, ALCM registration status per SKU where the awardee supplies DCR-mandated projects, Ind AS 20 conditional-grant recognition per milestone with Section 115JB MAT and Section 115BAA regime interaction, and Section 194Q code 1031 buyer-side TDS on inter-manufacturer wafer and cell sales above Rs 50 lakh per supplier per FY. Missing any hop defers the milestone-linked disbursement tranche and can either strand PLI-eligible capacity or open a Section 74 CGST exposure on cross-plant job-work movement.

How It's Resolved

Build a per-bidder capacity ledger keyed to the SECI Tranche-II LoA awarded capacity in MW, with the five-year milestone target expressed both as absolute MW and as percentage of awarded capacity (Y1 5 percent pilot, Y2 30 percent, Y3 60 percent, Y4 continuing ramp, Y5 100 percent). Ingest the applicant's SAP FI or Oracle Fusion sales ledger extract by HSN 8541.43 modules and HSN 8541.42 cells with per-SKU rated watt-peak for MW conversion, stamp each invoice with the module SKU and the ALCM registration flag where applicable, and reconcile the aggregated ERP MW output against the SECI portal milestone report for the year. Compute the per-year per-stage DVA workbook (polysilicon through wafer through cell through module) with landed-cost-of-imported-inputs pulled from ICEGATE Bill of Entry data and vendor-DVA certificates aggregated per Tier 1 vendor with the 50 percent haircut default for uncertified vendors, and cross-check the DVA achievement against the scheme floor for the year. Apply the per-MW indicative incentive band to the certified commissioned capacity for the year, bound by the LoA ceiling, and adjust for any facility commissioning penalty on the shortfall slice against the year's target (subject to force majeure exception review). Book the milestone-linked PLI grant receivable under Ind AS 20 on each milestone certification event with presentation choice between other income and net-of-depreciation, and compute the Section 115JB MAT book-profit adjustment on the recognition-basis grant tranche. Cross-check every inter-manufacturer wafer and cell sale for Section 194Q code 1031 buyer-side TDS above Rs 50 lakh per supplier per FY.

Configuration

Per-bidder capacity ledger with SECI Tranche-II LoA awarded capacity in MW as reference; five-year milestone target schedule (Y1 5 percent pilot, Y2 30 percent, Y3 60 percent, Y5 100 percent); HSN 8541.43 modules and HSN 8541.42 cells sales ledger with per-SKU rated watt-peak; ALCM registration status per SKU with certification expiry date; per-stage DVA workbook (polysilicon through wafer through cell through module) with per-stage bill-of-materials, vendor master, vendor-DVA certificate flag, and 50 percent haircut default; per-year DVA floor per scheme methodology; ICEGATE Bill of Entry ingestion for landed cost of imported polysilicon (HSN 2804.61), wafers (HSN 3818.00), cells (HSN 8541.42), and modules (HSN 8541.43); per-MW indicative incentive band per LoA (Tranche-II illustrative Rs 4,000 to Rs 6,000 per kW); LoA ceiling amount; facility commissioning penalty schedule per month of delay per LoA; force majeure exception claim register; third-party inspection agency (TPIA) empanelment list; Bureau of Indian Standards module-testing lab certification per SKU; SECI portal milestone reporting calendar; Ind AS 20 recognition template with presentation choice; Section 115JB MAT and Section 115BAA regime flag; Section 194Q code 1031 inter-manufacturer sales register; Section 143 CGST job-work register with Rule 45 challan and Form ITC-04 quarterly filings.

Output

A per-bidder Tranche-II milestone-linked PLI claim pack: the per-bidder capacity ledger reconciled against the SECI LoA awarded capacity with the five-year milestone target expressed in both MW and percentage terms; the year's certified commissioned capacity reconciliation against the year's target with any shortfall slice quantified for facility commissioning penalty exposure; the per-year per-stage DVA workbook (polysilicon through wafer through cell through module) with vendor-DVA-certificate coverage, ICEGATE Bill of Entry linkage, and vendor-DVA-with-and-without-haircut sensitivity view; the per-MW indicative incentive computation against the LoA ceiling with the ceiling-remaining balance explicit; the facility commissioning penalty calculation on the shortfall slice with the force majeure claim status flagged; the third-party inspection agency (TPIA) certification report and Bureau of Indian Standards (BIS) module-testing lab report per milestone; the ALCM registration status register per module SKU where DCR-project supply applies; the SECI portal milestone reporting workbook; and the accounting entry pack showing the milestone-linked PLI grant receivable, presentation choice under Ind AS 20, Section 115JB MAT book-profit adjustment, Section 115BAA regime flag, and Section 194Q code 1031 buyer-side TDS reconciliation on inter-manufacturer wafer and cell sales.

Each of the 11 successful bidders holding a Solar Energy Corporation of India Tranche-II Letter of Award from April 2023 — from an integrated manufacturer at the 6,000 MW awarded-capacity scale of Waaree Energies at the upper end down to First Solar Manufacturing at 600 MW at the lower end, and every capacity in between including Adani Infrastructure (2,000 MW under Tranche-II), Reliance New Energy Solar (6,000 MW), Tata Power Solar Systems (4,000 MW), ReNew Power (4,800 MW), Avaada Ventures (3,000 MW), Vikram Solar (2,400 MW), Grew Energy (2,000 MW), Indosol Solar (2,000 MW), and JSW Neo Energy (1,000 MW) — runs the same per-bidder five-year milestone reconciliation surface. This is PLI Solar Tranche-II SECI 39,600 MW 11 bidder reconciliation, and the discipline that keeps the per-bidder commissioning tracker, the Y1 pilot through Y5 full commercial capacity ramp, the per-MW indicative incentive computation against the LoA ceiling, the Y-o-Y DVA achievement against the scheme floor, and the facility commissioning penalty exposure under simultaneous control is what determines whether each year’s milestone disbursement tranche lands on schedule against SECI’s cycle.

The reconciliation in one paragraph

A SECI Tranche-II LoA holder runs a five-track reconciliation across the milestone-linked disbursement cycle. Track one is the per-bidder capacity ledger — the LoA awarded capacity in MW is the reference, the five-year target schedule expresses each year’s milestone in both absolute MW terms and as a percentage of awarded capacity (illustratively Year 1 pilot 5 percent, Year 2 30 percent, Year 3 60 percent, Year 5 100 percent), and the year’s certified commissioned capacity is reconciled against the year’s target with any shortfall quantified. Track two is the per-year per-stage DVA workbook running polysilicon through wafer through cell through module with per-stage bill-of-materials, vendor-DVA-certificate register, and 50 percent haircut default for uncertified vendors, cross-checked against the scheme’s per-year DVA floor for the applicant’s integration profile. Track three is the per-MW indicative incentive computation — the Tranche-II band is illustratively in the Rs 4,000 to Rs 6,000 per kW range, materially lower than the Tranche-I band of Rs 8,000 to Rs 12,000 per kW under IREDA reflecting the 4.5x larger Tranche-II pool and scheme evolution — bound by the LoA ceiling with the ceiling-remaining balance explicit at each milestone. Track four is the facility commissioning penalty exposure register — every shortfall slice against the year’s target carries a proportionate per-month-of-delay penalty on the delayed capacity, subject to force majeure exception review by MNRE and SECI where applicable. Track five is the accounting and tax overlay — Ind AS 20 conditional-grant recognition per milestone certification event, Section 115JB MAT book-profit adjustment on the recognition-basis tranche, Section 115BAA regime flag, and Section 194Q code 1031 buyer-side TDS on inter-manufacturer wafer and cell sales above Rs 50 lakh per supplier per FY. Terra Insight’s PLI Solar PV Modules Rs 24,000 crore MNRE claim reconciliation cornerstone situates the SECI Tranche-II mechanic within the broader two-tranche scheme (Tranche-I under IREDA plus Tranche-II under SECI), and reading that cornerstone first anchors the ministry-agency-outlay-award structure this article specialises into per-bidder detail.

What the scenario looks like in India — the 11-bidder pool

The SECI Tranche-II awardee pool announced in April 2023 spans an integrated cross-section of Indian solar PV manufacturers with facilities across Gujarat, Maharashtra, Tamil Nadu, Karnataka, Andhra Pradesh, Rajasthan, and other states. The 11-bidder distribution by awarded capacity: Waaree Energies (6,000 MW — integrated wafer-through-module capacity across Surat and Chikhli greenfield campuses in Gujarat), Adani Infrastructure (2,000 MW under Tranche-II layering on the 4,000 MW Tranche-I award to reach 6,000 MW cumulative — integrated Mundra facility in Gujarat with the Kutch Rs 20,000 crore expansion), Reliance New Energy Solar (6,000 MW — integrated giga-factory in Jamnagar, Gujarat), Tata Power Solar Systems (4,000 MW — Tirunelveli campus in Tamil Nadu), ReNew Power (4,800 MW — greenfield integrated capacity), Avaada Ventures (3,000 MW — greenfield capacity), Vikram Solar (2,400 MW — Panvel campus in Maharashtra with Tamil Nadu expansion), Grew Energy (2,000 MW — greenfield capacity), Indosol Solar (2,000 MW — greenfield capacity), JSW Neo Energy (1,000 MW), and First Solar Manufacturing (600 MW — Chennai integrated capacity, the sole non-Indian-heritage awardee).

For the illustrative worked example in this article, we take a Tranche-II integrated awardee at the scale of Waaree Energies with a 6,000 MW LoA dated April 2023 across the integrated Surat and Chikhli campuses. The persona is illustrative — Waaree’s actual SECI-issued LoA carries a specific per-MW indicative incentive band and a specific year-by-year milestone schedule that are commercial confidential inside the LoA text — and the numbers below are illustrative of the reconciliation grammar, not a claim about Waaree’s specific PLI position. The point of the persona is the per-bidder five-year milestone reconciliation surface, not any specific applicant’s exact commercial terms.

At the lower end of the pool, a 600 MW awardee at the scale of First Solar Manufacturing runs the same milestone grammar at a proportionately smaller scale — Y1 pilot target of 30 MW (5 percent), Y2 target of 180 MW (30 percent), Y3 target of 360 MW (60 percent), Y5 target of 600 MW (100 percent) — with the same per-MW indicative incentive band and the same per-year DVA floor mechanic. The PLI Solar Tranche-I IREDA 8,737 MW 3-bidder reconciliation Wave 3 sibling covers the equivalent mechanic for the earlier Tranche-I pool where the per-MW indicative incentive band is materially higher.

The regulatory overlay — SECI implementing agency, April 2023 LoA cycle, five-year milestone schedule

The SECI Tranche-II mechanic sits inside the broader MNRE PLI Solar PV Modules scheme. The Ministry of New and Renewable Energy administers the scheme with a total outlay of Rs 24,000 crore across two tranches. Tranche-I Rs 4,500 crore was implemented by the Indian Renewable Energy Development Agency (IREDA) with awards issued in November 2021 for 8,737 MW capacity across three selected bidders. Tranche-II Rs 19,500 crore was implemented by the Solar Energy Corporation of India (SECI) — a Public Sector Undertaking under MNRE’s administrative control — with awards issued in April 2023 for 39,600 MW capacity across 11 selected bidders. The Tranche-II pool is roughly 4.5 times the Tranche-I pool by MW capacity against roughly 4.3 times the Tranche-I outlay in rupee terms, which naturally moderates the per-MW indicative incentive band from the Tranche-I range (illustratively Rs 8,000 to Rs 12,000 per kW module rating) to the Tranche-II range (illustratively Rs 4,000 to Rs 6,000 per kW module rating).

Each SECI Tranche-II LoA carries five contractual components that drive the reconciliation surface. First, the awarded capacity in MW — ranging across the 11 bidders from 600 MW to 6,000 MW. Second, the per-MW indicative incentive band — a rupee-per-kW figure applied to the certified commissioned capacity per year, subject to the LoA ceiling. Third, the five-year commissioning milestone schedule — Year 1 pilot commissioning target (typically 5 percent of awarded capacity by 24 months from LoA), Year 2 target (typically 30 percent), Year 3 target (typically 60 percent), Year 4 continuing the ramp, and Year 5 target of 100 percent by April 2028 for the April 2023 LoA cohort. Fourth, the per-year DVA floor — the scheme sets a rising Y1 to Y5 DVA floor, with the integrated-line profile targeting Y1 20 to 25 percent scaling to Y5 40 to 45 percent, and the assemblers-only profile targeting Y1 15 percent scaling to Y5 30 percent. Fifth, the facility commissioning penalty schedule — a proportionate reduction in the per-MW incentive per month of delay beyond the year’s milestone target date, applied to the shortfall slice only, subject to force majeure exception review by MNRE and SECI where applicable.

The SECI portal milestone reporting cycle is the operational surface for each LoA holder. Each year, the applicant submits a milestone reporting package covering the year’s certified commissioned capacity (with third-party inspection agency certification and Bureau of Indian Standards module-testing lab report per SKU), the year’s per-stage DVA workbook (polysilicon through wafer through cell through module with vendor-DVA-certificate coverage), the year’s producer-invoiced sales register by HSN 8541.43 module and HSN 8541.42 cell for MW conversion cross-check, and — where applicable — the Approved List of Modules and Manufacturers (ALCM) registration status per SKU for Domestic Content Requirement (DCR) project supply eligibility. Each successful milestone certification triggers the year’s disbursement tranche computation against the per-MW indicative incentive band and the LoA ceiling. The integrated per-stage DVA mechanic and the ALCM registration cycle are elaborated in detail in DVA domestic value addition computation for PLI electronics and in the Wave 3 solar depth articles on PLI Solar wafer-cell-module integrated DVA computation reconciliation and PLI Solar ALCM Approved List domestic content reconciliation.

A worked example — a 6,000 MW Tranche-II awardee across the five-year milestone ramp

Illustrative — the following figures represent the operating pattern of a Tranche-II integrated PLI Solar PV participant at the scale of an integrated wafer-through-module manufacturer holding a SECI Letter of Award from April 2023 for 6,000 MW of awarded capacity across an integrated Gujarat-based facility. Public disclosures do not reveal the specific per-applicant SECI-issued LoA per-MW indicative incentive band or the exact year-by-year milestone schedule inside the LoA; the numbers below are illustrative of the reconciliation surface, not a claim about any specific real applicant’s PLI position. Each milestone-linked disbursement tranche is subject to the applicant’s LoA ceiling; the illustrative computation below shows the reconciliation grammar before ceiling binding.

The illustrative 6,000 MW Tranche-II awardee with an April 2023 LoA runs the five-year milestone ramp as follows:

Milestone yearFYTarget capacity (MW)Target percentageMilestone certification
Y1 (Pilot)2024-25300 MW5 percentTPIA pilot commissioning certificate, BIS lab report, SECI intimation
Y22025-261,800 MW30 percentAnnual capacity certification, DVA workbook Y2 floor achieved
Y32026-273,600 MW60 percentAnnual capacity certification, DVA workbook Y3 floor achieved
Y42027-28Ramp continuingRampAnnual capacity certification, DVA workbook Y4 floor achieved
Y52027-286,000 MW100 percentFull commercial capacity certification, DVA workbook Y5 floor achieved

At the illustrative Tranche-II midpoint per-MW incentive band of Rs 5,000 per kW module rating, the illustrative cumulative incentive commitment over the five-year window works out to 6,000 MW multiplied by 1,000 kW per MW multiplied by Rs 5,000 per kW, which equals Rs 3,000 crore of headline commitment — subject in practice to the specific LoA ceiling amount (which sits materially inside this headline computation), to the year-by-year DVA achievement gating, and to the facility commissioning penalty adjustment on any shortfall slice. The Incremental Sales Hurdle Tracker for PLI supports the Y-o-Y capacity certification and the per-MW output tracking that feeds the SECI portal milestone reporting workbook.

The Year 3 milestone reconciliation for the illustrative 6,000 MW awardee shows the following pattern. Target for Year 3 is 3,600 MW (60 percent of awarded capacity). Actual certified commissioned capacity at the milestone certification date is illustratively 3,300 MW (55 percent achieved). Shortfall against target is 300 MW, which commissions three months later. The facility commissioning penalty applies proportionately on the delayed 300 MW slice for the three-month delay period, reducing the per-MW incentive on that slice. The applicant files a force majeure claim citing global polysilicon supply-chain disruption on the delayed capacity, and MNRE-SECI joint review accepts a partial force majeure exception for two months of the three-month delay period, leaving the penalty applicable to one month of delay on the 300 MW slice. The illustrative per-MW incentive at the Tranche-II midpoint of Rs 5,000 per kW module rating is applied to the 3,300 MW achieved-on-time capacity plus the 300 MW delayed capacity net of the one-month facility commissioning penalty, and the total is bound by the year’s LoA ceiling allocation. The resulting disbursement tranche is recognised under Ind AS 20 when SECI issues the milestone certification and disbursement approval — presentation choice between other income and net-of-depreciation per the entity’s Ind AS 20 policy election. The reconciliation playbook monthly close for India pillar situates the milestone-linked recognition entries within the entity’s monthly close cadence, ensuring the SECI milestone certification event and the Ind AS 20 recognition entry land in the correct period.

Common reconciliation breakages

Five breakages recur across SECI Tranche-II per-bidder milestone reconciliation cycles.

  • Year’s certified commissioned capacity against year’s target MW figure and shortfall quantification gap. The SECI portal milestone reporting workbook requires the year’s certified commissioned capacity to be expressed both in absolute MW terms and as a percentage of the awarded capacity, cross-referenced against the year’s target. Where the applicant’s internal capacity certification and the SECI portal report drift by even a small MW figure (typically due to a mid-year commissioning event that straddles the milestone certification cut-off), the shortfall slice for facility commissioning penalty purposes is mis-quantified and the year’s disbursement tranche is either under- or over-computed. The reconciliation discipline is a strict cut-off date for the year’s certified commissioned capacity aligned to the milestone certification event, with a per-MW-added event log capturing any capacity addition after the cut-off for reporting into the following year.

  • Per-year per-stage DVA workbook and vendor-DVA certificate coverage gap. The integrated DVA computation depends on vendor-DVA certificate flags on every material Tier 1 vendor supplying each of the four stages. A missing certificate triggers the 50 percent haircut on that vendor’s supply value under scheme methodology, and where the missing vendor is a large glass or EVA or backsheet supplier, the haircut can drop the module-stage DVA below the scheme-set floor for the year, gating the milestone disbursement. The reconciliation discipline is a vendor master with a DVA certificate flag per tier per stage, an aging report of pending certificate collections, and a per-year per-stage DVA-with-and-without-haircut computation to expose the sensitivity before the SECI portal claim is submitted.

  • Facility commissioning penalty computation and force majeure claim status tracking gap. Every shortfall slice against the year’s target carries a facility commissioning penalty exposure that must be quantified per month of delay and reconciled against the year’s disbursement tranche computation. The force majeure exception claim status (pending, accepted in full, accepted in part, rejected) must be tracked per shortfall event because the acceptance outcome directly determines the applicable penalty. Where the applicant computes the year’s disbursement tranche assuming force majeure acceptance in full without SECI-MNRE confirmation, the actual disbursement can be materially lower and creates a book-tax timing issue on the Ind AS 20 recognition. The reconciliation failure-mode analysis for India methodology treats the shortfall-and-penalty leg as a specific failure mode with documented control tests.

  • Per-MW indicative incentive computation and LoA ceiling binding transparency gap. The per-MW indicative incentive is applied to the certified commissioned capacity for the year, but the year’s disbursement tranche is bound by the LoA ceiling and by the cumulative disbursement to date. Where the LoA ceiling remaining balance is not tracked explicitly across the five-year window, the year’s disbursement computation can overshoot the ceiling and require adjustment mid-cycle. The reconciliation discipline is an explicit LoA ceiling ledger showing cumulative disbursement to date, remaining balance, and the year’s tranche binding against the balance. Terra Insight’s Section 393 payment code finder supports the ancillary Section 194Q code 1031 buyer-side TDS discipline on inter-manufacturer wafer and cell sales that layers on top of the SECI disbursement cycle.

  • Ind AS 20 conditional-grant recognition timing on milestone certification event versus cash disbursement event. The applicant that recognises the milestone-linked grant tranche only on cash disbursement (rather than on SECI milestone certification and disbursement approval-letter issuance) creates a book-tax timing gap and can under-provision Section 115JB MAT for the period in which the milestone was certified but cash had not yet arrived. The recognition should trigger on the certification event; the cash-receipt event only settles the receivable balance. The 57 human errors and the detection envelope anchor treats this recognition-timing error class as a documented failure mode. The interaction with MAT and 115BAA transfers cleanly from the sister sectoral cornerstones in PLI vs MAT Minimum Alternate Tax pharma interaction and Section 115BAA vs PLI pharma concessional rate election.

How a reconciliation platform handles this

A purpose-built electronics reconciliation platform ingests the SECI Tranche-II Letter of Award awarded capacity in MW per bidder, the five-year milestone target schedule with year-by-year MW and percentage figures, the applicant’s SAP FI or Oracle Fusion sales ledger extract by HSN 8541.43 modules and HSN 8541.42 cells with per-SKU rated watt-peak for MW conversion, the year’s certified commissioned capacity per plant line with the third-party inspection agency certification date, the per-year per-stage DVA workbook (polysilicon through wafer through cell through module) with vendor master and vendor-DVA-certificate flag, the ICEGATE Bill of Entry register for landed cost of imported polysilicon (HSN 2804.61), wafers (HSN 3818.00), cells (HSN 8541.42), and modules (HSN 8541.43), the per-MW indicative incentive band per LoA with the LoA ceiling amount and cumulative disbursement to date, the facility commissioning penalty schedule per month of delay with the shortfall slice log and force majeure claim status per event, the ALCM registration status register per SKU with certification expiry dates, the Section 194Q code 1031 inter-manufacturer sales register above the Rs 50 lakh per supplier per FY threshold, the Section 143 CGST job-work register with Rule 45 challan and Form ITC-04 quarterly filings, and the Ind AS 20 recognition event register per milestone certification — and produces a per-bidder milestone-linked disbursement reconciliation workbook that closes the loop from ERP invoice line to SECI portal milestone reporting. Match rate improvement from 51 to 88 percent on the year’s MW capacity certification, the per-stage DVA vendor-certificate coverage, the facility commissioning penalty computation, the LoA ceiling binding, and the inter-manufacturer Section 194Q reconciliation — combined with an ISO 27001:2022 posture, AWS Mumbai residency, and DPDP Act 2023 aligned data handling — is what makes the platform an infrastructure investment for a Tranche-II awardee rather than a spreadsheet substitute. The commercial pillar for the sub-cluster is Electronics reconciliation software India; the broader authority is reconciliation software India.

Terra Insight
Terra Insight Editorial Team Reconciliation Infrastructure

Content authored by practitioners with experience at Amazon India, Intuit QuickBooks, and the Tata Group. Meet the team →

Published 22 July 2026
Domain expertise
TDS Reconciliation GST Input Credit Platform Settlements NACH Batch Matching Bank Reconciliation Form 26AS Matching ERP Integrations Enterprise Finance Ops
Primary reference: Solar Energy Corporation of India (SECI) — for the Tranche-II Rs 19,500 crore leg of the PLI High Efficiency Solar PV Modules scheme awarded April 2023 for 39,600 MW of integrated manufacturing capacity across 11 selected bidders, the per-bidder commissioning milestone schedule from Year 1 pilot through Year 5 full commercial capacity, and the SECI portal milestone reporting cycle that underpins each disbursement tranche.
Primary sources cited
Last reviewed against sources on 22 July 2026
  • Solar Energy Corporation of India (SECI) — PLI Tranche-II implementing agency — The Solar Energy Corporation of India Limited (SECI) is a Public Sector Undertaking under the administrative control of the Ministry of New and Renewable Energy (MNRE) and the designated implementing agency for Tranche-II of the PLI Scheme on National Programme on High Efficiency Solar PV Modules — Rs 19,500 crore outlay. SECI concluded the competitive bid process in March 2023 with Letters of Award (LoA) issued in April 2023 for 39,600 MW of integrated manufacturing capacity across 11 selected bidders. Each Letter of Award binds the successful bidder to establish fully-integrated manufacturing capacity covering polysilicon (where applicable), wafer, cell, and module stages, with a per-bidder commissioning milestone schedule ranging from pilot line commissioning within 24 months (Year 1 to Year 2) through full commercial capacity ramp by Year 5 from the LoA date. The SECI portal hosts the milestone reporting cycle covering commissioning intimation, third-party inspection agency reports, capacity certification, DVA achievement for the year, and disbursement claim submission against the applicant's per-MW indicative incentive band.
  • PLI Scheme on National Programme on High Efficiency Solar PV Modules, MNRE — The Production Linked Incentive Scheme for the National Programme on High Efficiency Solar PV Modules is administered by the Ministry of New and Renewable Energy with a total outlay of Rs 24,000 crore across two tranches. Tranche-I of Rs 4,500 crore was implemented by the Indian Renewable Energy Development Agency (IREDA) with awards issued in November 2021 for 8,737 MW capacity across three selected bidders. Tranche-II of Rs 19,500 crore was implemented by SECI with awards issued in April 2023 for 39,600 MW capacity across 11 selected bidders. The Tranche-II per-MW indicative incentive band is lower than Tranche-I (illustratively in the Rs 4,000 to Rs 6,000 per kW module rating range under Tranche-II versus Rs 8,000 to Rs 12,000 per kW under Tranche-I) reflecting the scheme evolution, the significantly larger 39,600 MW pool under Tranche-II versus 8,737 MW under Tranche-I, and the scheme intent to accelerate commodity-scale solar PV manufacturing at competitive per-MW incentive levels. Disbursement is milestone-linked over five to six years from the LoA date.
  • Press Information Bureau (PIB) — Tranche-II SECI Letter of Award announcement, April 2023 — The Press Information Bureau confirmed the SECI Letter of Award announcements in April 2023 for 39,600 MW of integrated solar PV manufacturing capacity across 11 selected bidders under Tranche-II of the MNRE PLI Solar PV Modules scheme. The awarded capacity pool was distributed across integrated manufacturers with facilities in Gujarat, Maharashtra, Tamil Nadu, Karnataka, Andhra Pradesh, Rajasthan, and other states, with individual awarded capacities ranging from 600 MW at the lower end to 6,000 MW at the upper end. The scheme intent as stated in the PIB release is to establish India as a globally-competitive integrated solar PV manufacturing hub with fully-domestic polysilicon-to-module capability and to reduce dependence on imported cells and modules from China and other manufacturing geographies.
  • Ind AS 20, Accounting for Government Grants and Disclosure of Government Assistance — Notified by the Ministry of Corporate Affairs as part of the Companies (Indian Accounting Standards) Rules 2015 and subsequent amendments. Government grants related to income are recognised in profit or loss on a systematic basis over the periods in which the entity recognises as expenses the related costs for which the grants are intended to compensate. The PLI Solar Tranche-II grant is a conditional grant tied to per-bidder commissioning milestones — Year 1 pilot commissioning through Year 5 full commercial capacity — with recognition on each milestone certification event when the entity has reasonable assurance that both the milestone will be achieved and the disbursement will be received. Presentation choice under Ind AS 20 is between other income (separate profit and loss line) and net-of-depreciation (netted against the depreciation charge on the capitalised plant and equipment).
  • Facility Commissioning Penalty and Force Majeure provisions, SECI Tranche-II LoA — Each SECI Tranche-II Letter of Award carries a facility commissioning penalty clause specifying a proportionate reduction in the per-MW indicative incentive per month of delay beyond the milestone target date for the year, subject to force majeure exception review by MNRE and SECI. The commissioning penalty applies to the missed-capacity portion of the year's target — for example, if a Year 2 target of 1,800 MW is achieved at 1,200 MW by the milestone date and the balance 600 MW commissions six months later, the facility commissioning penalty applies proportionately on the delayed 600 MW slice. The penalty is a deduction from the eligible disbursement tranche for that year and does not reduce the LoA ceiling but does compress the effective per-MW incentive earned for the delayed capacity.

Frequently Asked Questions

How many bidders received PLI Solar Tranche-II Letters of Award from SECI in April 2023, and what is the total awarded capacity?
The Solar Energy Corporation of India (SECI) issued Letters of Award (LoA) in April 2023 to 11 selected bidders under Tranche-II of the MNRE PLI Scheme on National Programme on High Efficiency Solar PV Modules for a combined 39,600 MW of integrated manufacturing capacity, against a Tranche-II outlay of Rs 19,500 crore. The 11-bidder pool includes: Waaree Energies with 6,000 MW, Adani Infrastructure with 2,000 MW under Tranche-II (Adani cumulative across Tranche-I and Tranche-II reaches 6,000 MW), Reliance New Energy Solar with 6,000 MW, Tata Power Solar Systems with 4,000 MW, Vikram Solar with 2,400 MW, ReNew Power with 4,800 MW, Avaada Ventures with 3,000 MW, Grew Energy with 2,000 MW, JSW Neo Energy with 1,000 MW, First Solar Manufacturing with 600 MW, and Indosol Solar with 2,000 MW — totalling 39,600 MW. Each LoA binds the successful bidder to establish fully-integrated manufacturing capacity from wafer (or polysilicon where applicable) through cell to module and to commission the awarded capacity over a five-year milestone-linked schedule from the LoA date of April 2023.
What is the Year 1 through Year 5 commissioning milestone ramp under the SECI Tranche-II Letter of Award, and how does it work for an illustrative 6,000 MW awardee?
Each SECI Tranche-II LoA carries a per-bidder commissioning milestone schedule that ramps from Year 1 pilot commissioning through Year 5 full commercial capacity, with the milestone target expressed both as an absolute MW figure and as a percentage of the awarded capacity. For an illustrative 6,000 MW awardee at the scale of Waaree Energies with a Tranche-II LoA dated April 2023, the milestone ramp progresses as: Year 1 pilot commissioning target of 300 MW (5 percent of awarded capacity) by April 2024, Year 2 target of 1,800 MW (30 percent) by April 2025, Year 3 target of 3,600 MW (60 percent) by April 2026, Year 4 target continuing the ramp, and Year 5 target of 6,000 MW (100 percent) by April 2028. Each milestone is certified by a third-party inspection agency (TPIA), reported through the SECI portal milestone reporting cycle, and triggers the per-year disbursement tranche computation against the applicant's per-MW indicative incentive band. Missing a milestone target for the year triggers the facility commissioning penalty on the shortfall slice — a proportionate reduction in the per-MW incentive on the missed capacity — subject to force majeure exception review by MNRE and SECI where applicable.
What is the per-MW indicative incentive band under SECI Tranche-II and why is it lower than the Tranche-I band under IREDA?
The per-MW indicative incentive band under SECI Tranche-II is illustratively in the Rs 4,000 to Rs 6,000 per kW of module rating range, materially lower than the Tranche-I band under IREDA which was illustratively in the Rs 8,000 to Rs 12,000 per kW range. The difference reflects three factors. First, scheme evolution — Tranche-I in November 2021 was the initial scheme leg carrying a higher per-MW incentive to attract the first anchor investment cases, while Tranche-II in April 2023 followed with a moderated per-MW rate at a broader participation base. Second, the pool size difference — Tranche-I awarded 8,737 MW across 3 bidders while Tranche-II awarded 39,600 MW across 11 bidders, requiring the fixed Rs 19,500 crore Tranche-II outlay to be distributed across roughly 4.5 times the Tranche-I capacity, which naturally compresses the per-MW average. Third, scheme intent — the Tranche-II design aims for commodity-scale competitive solar PV manufacturing, and the moderated per-MW rate is priced at a level that rewards efficient integrated manufacturers while not over-subsidising later entrants. For a 6,000 MW awardee at the Tranche-II midpoint of Rs 5,000 per kW, the illustrative cumulative incentive commitment over the five-year window works out to approximately Rs 300 crore (6,000,000 kW multiplied by Rs 5,000 per kW equals Rs 3,000 crore, subject to the LoA ceiling and DVA-achievement gating — the specific ceiling and the year-by-year disbursement schedule are set inside each LoA and are commercial confidential).
How does per-bidder DVA achievement Y1 through Y5 flow into the milestone-linked disbursement, and what is the reconciliation surface for the DVA workbook per year?
The per-bidder Domestic Value Addition (DVA) achievement Y1 through Y5 is one of the two gating conditions for each year's milestone disbursement — the other being the capacity commissioning target. DVA is computed as (Ex-factory sale value minus Landed cost of imported inputs) divided by Ex-factory sale value, expressed as a percentage of ex-factory revenue. The scheme sets a DVA floor for each year that rises across the five-year window — an integrated line typically targets Y1 20 to 25 percent scaling to Y5 40 to 45 percent, while an assemblers-only line typically targets Y1 15 percent scaling to Y5 30 percent. The reconciliation surface is a per-year per-stage DVA workbook that runs polysilicon (Stage 1) through wafer (Stage 2) through cell (Stage 3) through module assembly (Stage 4), with each stage carrying its own bill-of-materials, vendor master, and vendor-DVA certificate flag. Where a Tier 1 vendor has not supplied a vendor-DVA certificate, a 50 percent haircut applies to that vendor's supply value under the scheme methodology — the same haircut mechanic covered in Wave 1 for the MeitY LSEM DVA framework. The DVA workbook for the year feeds the SECI portal claim submission alongside the capacity certification, and both must clear the year's floor for the milestone disbursement to trigger.
What is the facility commissioning penalty for delay under a SECI Tranche-II LoA, and how does force majeure exception review operate?
Each SECI Tranche-II LoA carries a facility commissioning penalty clause that specifies a proportionate reduction in the per-MW indicative incentive per month of delay beyond the milestone target date for the year. The penalty applies to the missed-capacity slice — for example, if a Year 3 target of 3,600 MW is achieved at 3,000 MW by the milestone date and the balance 600 MW commissions three months later, the facility commissioning penalty applies proportionately on the delayed 600 MW slice for the three-month delay period. The penalty is a deduction from the eligible disbursement tranche for that year and does not reduce the LoA ceiling but does compress the effective per-MW incentive earned for the delayed capacity. Force majeure exception review is available where the delay is attributable to events beyond the applicant's control — global supply-chain disruption on imported equipment (diffusion furnaces, wire saws, lamination lines), international polysilicon supply shocks, statutory delays in land or environmental clearance, and similar categories — and MNRE and SECI jointly review the force majeure claim. Where accepted, the milestone target date is extended by the force majeure period and no penalty applies. Where rejected, the facility commissioning penalty applies in full. The reconciliation discipline is a per-milestone shortfall log with the delay period, the missed-capacity MW figure, the force majeure claim status, and the resulting adjusted disbursement computation for the year.

See how TransactIG handles reconciliation for your industry

Configuration takes 2–4 weeks. No code development required. ISO 27001:2022 certified.