Skip to main content
How-To · 14 min read

PLI Solar Manufacturing Facility Commissioning Milestone Reconciliation

An MNRE PLI Tranche-II integrated solar PV manufacturer awarded a Letter of Award by SECI in April 2023 for MW-scale integrated capacity must reconcile the milestone-linked disbursement calendar against the LoA schedule — pilot line by 24 months from LoA date, partial commercial capacity through Year 2 and Year 3, full commercial capacity through Year 4 and Year 5. Each milestone certification requires SECI/IREDA-appointed CA statutory-auditor-style capex certification, OEM equipment vendor invoice with delivery and installation proof, technology partner process-readiness certification, BIS wafer/cell/module certification, and IEC 61215 plus IEC 61730 module type-approval reports. Miss any hop and the milestone-linked tranche defers, or the per-MW indicative incentive suffers the penalty-schedule reduction for the months of delay outside the MNRE force-majeure exception envelope.

Terra Insight
Terra Insight Editorial Team Reconciliation Infrastructure

Content authored by practitioners with experience at Amazon India, Intuit QuickBooks, and the Tata Group. Meet the team →

Published 22 July 2026
Domain expertise
TDS Reconciliation GST Input Credit Platform Settlements NACH Batch Matching Bank Reconciliation Form 26AS Matching ERP Integrations Enterprise Finance Ops
Knowledge Card
Problem

An MNRE PLI Tranche-II integrated solar PV manufacturer holding a SECI-issued Letter of Award from April 2023 for a specific MW-scale integrated manufacturing capacity must reconcile the milestone-linked disbursement calendar (pilot line by 24 months from LoA date, partial commercial through Year 2 and Year 3, full commercial through Year 4 and Year 5) against a five-part certification pack per milestone: SECI/IREDA-appointed chartered accountant capex certification, OEM equipment vendor invoice with delivery and installation proof, technology partner process-readiness certification, BIS product certification against IS 14286 and IS 61730, and IEC 61215 and IEC 61730 module type-approval test reports from an IEC-accredited laboratory. Any missing certification defers the milestone tranche; any slippage beyond the LoA target date triggers a per-MW indicative incentive penalty schedule (typically a percentage reduction per month of delay on the affected capacity portion) unless an MNRE force-majeure exception request is filed and granted for documented exception heads (monsoon-window civil works, supply-chain disruption on imported equipment, technology-transfer delays). The reduced tranche flows through Ind AS 20 conditional-grant recognition and the Section 115JB MAT book-profit adjustment at the reduced amount.

How It's Resolved

Build a milestone calendar tracker keyed to each plant line (polysilicon, wafer, cell, module) with the SECI Letter of Award milestone target dates as the reference — pilot commissioning target = LoA date plus 24 months, partial commercial capacity ramp through Year 2 and Year 3, full commercial capacity through Year 4 and Year 5. Attach a capex-per-milestone workbook keyed to the equipment purchase order register, tied out to the ICEGATE Bill of Entry data for imported equipment, GRIR balances, capitalisation cut-off tests, and the fixed asset register. Maintain a per-milestone certification status register with five certification lines: CA capex certification (SECI/IREDA-appointed CA identity, certification date, capex certified amount), OEM equipment vendor invoice and installation proof register per equipment line, technology partner process-readiness certification (partner identity, process license reference, certification date), BIS product certification register per SKU (IS 14286 and IS 61730 certification date, expiry, testing lab), and IEC test report register per SKU (IEC 61215 and IEC 61730 test lab, report date, expiry). Compute the milestone penalty variance per LoA schedule — for each month of slippage beyond the LoA target date, apply the per-MW indicative incentive penalty percentage on the delayed capacity portion. Maintain a parallel force-majeure claim register (event date, exception head, documentary evidence pack, MNRE decision, re-baselined milestone date). Book the Ind AS 20 grant tranche at the amount actually receivable (nominal or reduced) on SECI milestone certification and approval-letter issuance, and flow the Section 115JB MAT book-profit adjustment on that recognised amount.

Configuration

Milestone calendar tracker per plant line with SECI LoA target dates (pilot 24 months from LoA, partial commercial Year 2 and Year 3, full commercial Year 4 and Year 5); capex-per-milestone workbook keyed to equipment PO register and audited fixed asset register with ICEGATE Bill of Entry linkage for imported equipment; CA capex certification register (SECI/IREDA-appointed CA identity, certification date, certified amount, workpaper reference); OEM equipment invoice and installation proof register per equipment line (OEM identity, PO reference, invoice number, delivery challan, installation completion certificate); technology partner process-readiness certification register (partner identity, process license reference, certification date, applicable technology-node coverage); BIS product certification register per SKU (IS 14286 and IS 61730 test lab, certification date, expiry); IEC test report register per SKU (IEC 61215 and IEC 61730 test lab, report date, expiry, standards version); milestone penalty variance calculation per LoA schedule (per-MW indicative incentive penalty percentage per month of slippage on delayed capacity portion); force-majeure claim register (event date, exception head such as monsoon-window civil works or supply-chain disruption or technology-transfer delay, documentary evidence pack, MNRE decision, re-baselined milestone date); Ind AS 20 recognition trigger keyed to SECI milestone certification and approval-letter issuance; Section 115JB MAT book-profit adjustment on recognised tranche.

Output

A milestone-linked commissioning reconciliation pack per SECI milestone: the milestone calendar tracker per plant line reconciled against the LoA target dates with slippage variance quantified; the capex-per-milestone workbook tied out to the equipment PO register, ICEGATE BoE, and audited fixed asset register with CWIP-versus-capitalised cut-off tests; the five-line certification status register per milestone (CA capex, OEM equipment invoice and installation, technology partner process readiness, BIS IS 14286 and IS 61730 per SKU, IEC 61215 and IEC 61730 per SKU) with any missing certification exposed as an exception; the penalty variance calculation showing the per-month percentage reduction applied to the delayed capacity portion at the LoA per-MW indicative incentive band; the force-majeure claim register showing any pending or granted exception requests with documentary evidence pack and MNRE decision; the Ind AS 20 recognition entry at the amount actually receivable (nominal or reduced) with the Section 115JB MAT book-profit adjustment line; and the SECI portal milestone reporting workbook assembled and ready for submission.

An MNRE PLI Tranche-II integrated solar PV manufacturer at the scale of Vikram Solar — running the Panvel campus in Maharashtra alongside the Kolkata legacy line, and holding a SECI-issued Letter of Award from April 2023 for 2,400 MW of integrated manufacturing capacity — closes each milestone tranche of the PLI Solar PV Modules Rs 24,000 crore scheme with a five-part certification pack simultaneously in view: a SECI/IREDA-appointed chartered accountant capex certification, an OEM equipment vendor invoice with delivery and installation proof register, a technology partner process-readiness certification, a BIS product certification against IS 14286 and IS 61730, and an IEC 61215 plus IEC 61730 test report from an IEC-accredited laboratory. This is PLI Solar manufacturing facility commissioning milestone reconciliation at operating scale for a Tranche-II integrated awardee, and the discipline that keeps the milestone calendar tracker, the capex-per-milestone workbook, the five-line certification register, the penalty variance calculation, and the force-majeure claim register simultaneously clean is what separates a Tranche-II bidder whose milestone tranches disburse at nominal ceiling from one that spends the following financial year litigating a slippage penalty schedule reduction with SECI or waiting on an MNRE force-majeure exception decision.

Quick reference

AspectDetail
Scheme administratorMinistry of New and Renewable Energy (MNRE)
Tranche-II implementing agencySolar Energy Corporation of India (SECI)
Tranche-II award dateApril 2023
Tranche-II awarded capacity39,600 MW across 11 bidders
Milestone Y1 (pilot line)Typically 24 months from LoA date
Milestone Y2-Y3Partial commercial capacity ramp
Milestone Y4-Y5Full commercial capacity
Certification line 1SECI/IREDA-appointed CA capex certification
Certification line 2OEM equipment invoice, delivery, installation proof
Certification line 3Technology partner process-readiness certification
Certification line 4BIS IS 14286 (module design) and IS 61730 (safety)
Certification line 5IEC 61215 design qualification and IEC 61730 safety
Slippage penalty (illustrative)~0.5 percent per month reduction in per-MW incentive
Force-majeure headsMonsoon-window civil works, supply-chain, tech transfer
Accounting standardInd AS 20 conditional-grant recognition per milestone
Tax overlaySection 115JB MAT book-profit on recognised tranche

The reconciliation in one paragraph

A Tranche-II integrated solar PV manufacturer runs a five-surface reconciliation cascade across each milestone certification event. Surface one is the milestone calendar tracker — one row per plant line (polysilicon, wafer, cell, module), keyed to the SECI Letter of Award milestone target dates (pilot commissioning at LoA date plus 24 months, partial commercial through Year 2 and Year 3, full commercial through Year 4 and Year 5), with a live slippage variance column showing days ahead or behind the target. Surface two is the capex-per-milestone workbook — the equipment purchase order register tied out to the audited fixed asset register, with ICEGATE Bill of Entry linkage for imported equipment, GRIR balances cleared at year-end, and CWIP-versus-capitalised cut-off tests that mark which equipment is under construction and which is commissioned and depreciable. Surface three is the five-line certification status register per milestone — SECI/IREDA-appointed chartered accountant capex certification, OEM equipment vendor invoice with delivery challan and installation completion certificate per equipment line, technology partner process-readiness certification (the process-licensing OEM for the cell diffusion or module lamination line certifies process readiness), BIS product certification against IS 14286 (module design qualification, the Indian adoption of IEC 61215) and IS 61730 (module safety qualification), and IEC 61215 plus IEC 61730 test reports from an IEC-accredited laboratory for export-marketed SKUs. Surface four is the penalty variance calculation — for each month of slippage beyond the LoA target date, the per-MW indicative incentive penalty percentage applies to the delayed capacity portion, and the reconciliation exposes the resulting reduction in the milestone tranche. Surface five is the force-majeure claim register — a parallel ledger of exception requests filed with MNRE (event date, exception head, documentary evidence pack, MNRE decision, re-baselined milestone date if granted) that runs alongside the milestone calendar and pauses the penalty variance calculation on any milestone that is under active force-majeure review. The full cornerstone treatment of the surrounding scheme mechanics — Tranche-I versus Tranche-II split, integrated wafer-to-module DVA, ALCM registration, and Ind AS 20 recognition — sits in the PLI Solar PV Modules Rs 24,000 crore MNRE claim reconciliation cornerstone.

What the scenario looks like in India — the illustrative persona

The Tranche-II awardee pool implemented by SECI in April 2023 covers 11 integrated bidders across a total 39,600 MW awarded capacity: Waaree Energies (Surat and Chikhli integrated facility), Adani Infrastructure (Mundra Gujarat, combining Tranche-I and Tranche-II positions), Reliance New Energy Solar (Jamnagar integrated giga-factory), Tata Power Solar Systems (Tirunelveli Tamil Nadu), Vikram Solar (Panvel Maharashtra alongside the Kolkata legacy line), ReNew Power, Avaada Ventures, Grew Energy, JSW Neo Energy, First Solar Manufacturing, and Indosol Solar. Each holds an LoA with an awarded capacity, a per-MW indicative incentive band, and a milestone-linked disbursement schedule from the LoA date. The Tranche-I awardee pool implemented by IREDA in November 2021 covers a smaller three-bidder set (Adani Infrastructure 4,000 MW, Reliance New Energy 4,000 MW commitment, Shirdi Sai Electricals 737 MW) with a similar but tranche-specific milestone structure.

For the illustrative worked example in this article, we take a Tranche-II integrated participant at the scale of Vikram Solar running the Panvel Maharashtra campus with a 2,400 MW awarded capacity under the April 2023 LoA. The persona is illustrative; Vikram Solar’s real SECI-issued LoA and its per-MW indicative incentive band inside the LoA are governed by the confidential SECI bid outcome, and the numbers below illustrate the milestone reconciliation surface rather than any claim about Vikram’s specific PLI position. The point of the persona is the milestone-linked commissioning discipline, not any specific applicant’s exact awarded capacity or per-MW incentive band.

The multi-plant configuration for Panvel and Kolkata combined complicates the milestone tracker — capex-per-milestone workbook consolidation must run across the two-campus fixed asset register, GST-Rule-45 challans and Form ITC-04 filings cover cross-plant material movement between Panvel wafer feed and Kolkata legacy module lamination on distinct GSTINs, and BIS certification per SKU must be maintained per plant location because BIS certifies the manufacturing site as well as the SKU design. The multi-plant multi-GSTIN reconciliation grammar is elaborated for the wider integrated wafer-through-module case in PLI Solar wafer-cell-module integrated DVA computation reconciliation.

The regulatory overlay — MNRE scheme rulebook, SECI milestone certification, BIS and IEC standards, Ind AS 20

The MNRE PLI Solar PV Modules scheme rulebook (Rs 24,000 crore total outlay across two tranches) prescribes a milestone-linked disbursement calendar over five to six years from the LoA date. The pilot line commissioning milestone is typically due within 24 months of the LoA date — for a bidder with an April 2023 Tranche-II LoA, this lands pilot commissioning at April 2025 (FY 2024-25 close). Partial commercial capacity ramp is scheduled through Year 2 and Year 3 of the LoA (FY 2024-25 through FY 2025-26), and full commercial capacity is scheduled for Year 4 and Year 5 (FY 2026-27 and FY 2027-28). Each milestone triggers a disbursement tranche against the LoA ceiling, and each tranche requires a full certification pack.

SECI’s milestone certification workflow requires five certification lines. Line one is the CA capex certification — SECI or IREDA appoints or empanels a chartered accountant to perform a statutory-auditor-style verification of the capex claimed against the milestone. The CA reconciles the equipment purchase order register to the audited fixed asset register, ties out the imported equipment landed cost against ICEGATE Bill of Entry data and IGST paid at customs, confirms GRIR balances cleared at year-end, applies capitalisation cut-off tests (CWIP versus commissioned and depreciable), matches contractor and civil-works billing against the progress-billing schedule, and issues a signed certification statement. Line two is the OEM equipment vendor invoice register — for each imported equipment line (diffusion furnaces for cell production typically imported from Asian OEMs, wire saws for wafer slicing, module lamination lines, EL testers, sun simulators) the applicant maintains the PO, the OEM invoice, the shipping documents, the delivery challan at the plant, the installation completion certificate signed by the OEM engineer, and the commissioning readiness proof. Line three is the technology partner process-readiness certification — the process-licensing OEM (for a cell diffusion or module lamination line) certifies that the applicant’s staff has been trained on the licensed process, the line is capable of producing to the licensed specifications, and the process is ready for commercial commissioning. Line four is the BIS product certification against IS 14286 (Indian adoption of IEC 61215, crystalline silicon terrestrial PV module design qualification and type approval) and IS 61730 Parts 1 and 2 (Indian adoption of IEC 61730, module safety qualification). Line five is the IEC 61215 and IEC 61730 test reports from an IEC-accredited laboratory for export-marketed SKUs.

The MNRE force-majeure review provision under the scheme rulebook allows an applicant to request exemption from the per-MW indicative incentive penalty schedule for milestone slippage attributable to documented exceptions. The commonly-invoked exception heads are: monsoon-window civil-works delay affecting greenfield plant construction (the Indian Meteorological Department data supports the exception where the monsoon extended beyond the historically-typical envelope), supply-chain disruption on imported equipment (the diffusion furnaces, wire saws, and lamination lines are typically imported from a small set of specialised Asian OEMs and are exposed to shipping and lead-time disruption), and technology-transfer delays from the process-licensing OEM (correspondence with the OEM documents the delay). The exception request must be filed with a documentary evidence pack, MNRE reviews and either grants a re-baselining of the milestone date without penalty or denies the request and confirms the penalty schedule reduction.

Ind AS 20 conditional-grant recognition operates on each milestone certification event — the pilot commissioning triggers pilot tranche recognition, each subsequent capacity certification triggers that year’s tranche. Where a slippage penalty applies, the recognised amount is the reduced amount; where a force-majeure exception is pending, the tranche is not recognised until the exception is granted (re-baselined milestone with no penalty) or denied (recognise the reduced amount). The Section 115JB MAT book-profit adjustment flows through on the recognised amount for the period. The Ind AS 20 mechanics and the interaction with Section 115BAA concessional-rate election are elaborated at the cross-cluster PLI vs MAT Minimum Alternate Tax pharma interaction walkthrough, and the same mechanic transfers cleanly to the MNRE solar milestone recognition case.

A worked example — a Tranche-II 2,400 MW LoA integrated participant across the pilot commissioning cycle

Illustrative — the following figures represent the operating pattern of a Tranche-II integrated PLI Solar PV participant at the scale of an integrated Panvel-and-Kolkata manufacturer holding a SECI Letter of Award from April 2023 for 2,400 MW awarded capacity. Public disclosures do not reveal the per-applicant per-MW indicative incentive band inside the LoA, nor the exact per-month penalty percentage on slippage; the numbers below are illustrative of the reconciliation surface. Each milestone-linked disbursement tranche is subject to the applicant’s LoA ceiling; the illustrative computation below shows the reconciliation grammar and penalty flow before ceiling binding.

A Tranche-II integrated participant with an integrated Panvel plus Kolkata operating footprint receives a SECI Letter of Award in April 2023 for 2,400 MW of integrated manufacturing capacity at an illustrative per-kW indicative incentive of Rs 5,500. The pilot commissioning milestone is targeted at April 2025 for a rated pilot capacity of 120 MW.

The actual pilot commissioning event lands in May 2025 (one month slippage) at a rated pilot capacity of 100 MW (against the 120 MW target). The applicant submits the pilot commissioning certification pack to SECI on the May 2025 commissioning event.

Certification lineContentStatus at pilot milestone
CA capex certificationSECI-appointed CA statutory-auditor-style capex verificationSigned May 2025, capex certified Rs 850 crore against pilot line
OEM equipment invoice and installationDiffusion furnace + wire saw + lamination line + EL tester + sun simulatorFull pack per equipment line, installation certificates dated April to May 2025
Technology partner process-readinessCell diffusion and module lamination process-licensing OEM certificationSigned May 2025
BIS IS 14286 + IS 61730 per SKUModule design qualification + safety qualification3 pilot SKUs certified April 2025, 2 SKUs certification in progress
IEC 61215 + IEC 61730 per SKUIEC-accredited lab test reports3 pilot SKUs certified April 2025

The milestone penalty variance calculation applies the illustrative 0.5 percent per-month per-MW incentive reduction on the delayed pilot capacity portion. On the 100 MW pilot commissioned in May 2025 at the illustrative Rs 5,500 per kW indicative incentive, the pilot tranche notional value is Rs 55 crore (100 MW multiplied by 1,000 kW per MW multiplied by Rs 5,500 per kW). Applying a 0.5 percent reduction on the one-month slippage yields a Rs 27.5 lakh reduction on the pilot tranche, and the recognised tranche amount is approximately Rs 54.72 crore.

ItemValue (Illustrative)
Pilot capacity target (April 2025)120 MW
Pilot capacity actual (May 2025)100 MW (delayed 1 month)
Per-kW indicative incentiveRs 5,500
Pilot tranche nominal (100 MW × 1,000 × Rs 5,500)Rs 55 crore
Slippage penalty (0.5 percent × 1 month × 100 MW portion)Rs 27.5 lakh reduction
Recognised tranche under Ind AS 20Rs 54.72 crore (illustrative)
Section 115JB MAT book-profit adjustmentOn Rs 54.72 crore recognised amount

The applicant simultaneously files a force-majeure exception request citing monsoon-window civil-works delay in October 2024 (the Panvel campus civil works ran two weeks beyond the planned schedule owing to a documented extended monsoon), and submits IMD meteorological data as documentary evidence. MNRE reviews the request over Q3 FY 2025-26. If granted, the milestone is re-baselined to a May 2025 target date, the penalty variance drops to zero, and the recognised tranche moves to the full Rs 55 crore nominal with a prior-period recognition adjustment for the delta booked in the period in which the exception is granted. If denied, the recognised Rs 54.72 crore stands.

The reconciliation playbook monthly close pillar situates the milestone recognition entries and the force-majeure claim register within the entity’s monthly close cadence — the milestone certification event, the SECI approval letter, and the force-majeure decision date each trigger a close-cycle recognition entry that must not drift into the following month.

Common reconciliation breakages

Five breakages recur across PLI Solar milestone commissioning cycles.

  • Milestone calendar tracker not tied to SECI LoA target dates. Where the applicant’s project management tool tracks internal go-live dates but the milestone calendar does not carry the SECI LoA target dates as the reference, the slippage variance is not visible until the pilot commissioning event lands. The reconciliation discipline is to lift the LoA target dates (pilot at LoA plus 24 months, partial commercial through Year 2 and Year 3, full commercial through Year 4 and Year 5) directly from the LoA document and lock them as the target column on the milestone tracker.

  • Capex-per-milestone workbook not tied out to audited fixed asset register. Where the equipment PO register carries capex claimed but is not reconciled to the audited fixed asset register with CWIP-versus-capitalised cut-off tests, the CA capex certification either cannot be issued or is issued at a reduced amount. The reconciliation discipline is a monthly tie-out between the PO register, the GRIR ledger, and the fixed asset register, with the CWIP cut-off applied at each milestone commissioning event so that only commissioned equipment counts toward the capex claim.

  • Missing OEM installation completion certificate on imported equipment. Where the OEM engineer’s installation completion certificate is not obtained (typically because the OEM engineer left the site after preliminary installation without signing off the commissioning readiness), the milestone certification pack is incomplete and SECI defers the disbursement. The reconciliation discipline is a per-equipment-line certification tracker with the OEM installation certificate as a mandatory field and an aging report on pending certificates.

  • BIS certification per SKU per plant location. BIS certifies the manufacturing site alongside the SKU design — a SKU certified for Plant A cannot automatically be counted toward Plant B commissioning without a separate BIS re-testing for the Plant B site. Where the applicant runs multi-plant operations (Panvel plus Kolkata combined) and assumes a single-site BIS certification covers both plants, the milestone certification for the second plant is deferred. The PLI Solar wafer-cell-module integrated DVA computation reconciliation sibling covers the analogous per-plant per-stage discipline for the DVA workbook side. Terra Insight’s Section 393 payment code finder tool also supports the vendor-side tax reconciliation grammar (Section 194Q code 1031 buyer-side TDS) that runs across the equipment vendor register.

  • Force-majeure claim register maintained separately from milestone calendar or not maintained at all. Where the force-majeure exception request is filed but not linked to the corresponding milestone in the calendar tracker, the penalty variance calculation continues to accrue as if no exception was pending, and the Ind AS 20 recognition entry either books the reduced tranche (understating expected receivable) or books the nominal tranche (creating prior-period adjustment risk if the exception is denied). The reconciliation failure-mode analysis for India methodology treats the parallel-register linkage as a specific failure mode with documented control tests, and the 57 human errors and the detection envelope trust asset situates the recognition-timing error class within the wider taxonomy.

How a reconciliation platform handles this

A purpose-built electronics reconciliation platform ingests the SECI Letter of Award (awarded capacity per plant line, milestone target dates, per-MW indicative incentive band, LoA ceiling), the applicant’s equipment purchase order register, the audited fixed asset register with CWIP-versus-capitalised flags, the ICEGATE Bill of Entry data for imported equipment landed cost and IGST paid, the OEM equipment vendor invoice and installation certification register per equipment line, the technology partner process-readiness certification register, the BIS product certification register per SKU per plant (IS 14286 and IS 61730 test lab, certification date, expiry), the IEC 61215 and IEC 61730 test report register per SKU, the SECI/IREDA-appointed CA capex certification pack, and the force-majeure exception request register — and produces a milestone-linked disbursement reconciliation workbook that closes the loop from equipment PO to SECI portal milestone reporting. The platform runs the milestone calendar tracker with slippage variance highlighted at each milestone commissioning event, drives the capex-per-milestone workbook with CWIP cut-off tests and CA-workpaper alignment, exposes any missing certification line as an exception, computes the per-month penalty variance on delayed capacity portions with the force-majeure claim register linkage that pauses the calculation on active exception requests, and drives the Ind AS 20 conditional-grant recognition entry at the amount actually receivable (nominal or reduced) on SECI milestone certification and approval-letter issuance with the Section 115JB MAT book-profit adjustment. Match rate improvement from 51 to 88 percent on the milestone tracker, capex workbook, five-line certification register, penalty variance, and force-majeure recognition alignment — combined with an ISO 27001:2022 posture, AWS Mumbai residency, and DPDP Act 2023 aligned data handling — is what makes the platform an infrastructure investment for a Tranche-II integrated awardee rather than a spreadsheet substitute. The commercial pillar for the sub-cluster is Electronics reconciliation software India; the broader authority is reconciliation software India.

Terra Insight
Terra Insight Editorial Team Reconciliation Infrastructure

Content authored by practitioners with experience at Amazon India, Intuit QuickBooks, and the Tata Group. Meet the team →

Published 22 July 2026
Domain expertise
TDS Reconciliation GST Input Credit Platform Settlements NACH Batch Matching Bank Reconciliation Form 26AS Matching ERP Integrations Enterprise Finance Ops
Primary reference: Solar Energy Corporation of India (SECI) — for the PLI Tranche-II Rs 19,500 crore implementation covering 39,600 MW of integrated manufacturing capacity awarded April 2023, the milestone-linked disbursement schedule from pilot line commissioning (24 months from LoA) through full commercial capacity (Year 4 and Year 5), the third-party inspection agency and Bureau of Indian Standards certification cycle for milestone certification, and the MNRE force-majeure review provision for schedule variance driven by monsoon-window delays or supply-chain disruptions.
Primary sources cited
Last reviewed against sources on 22 July 2026
  • PLI Scheme on National Programme on High Efficiency Solar PV Modules, MNRE — Administered by the Ministry of New and Renewable Energy with total outlay Rs 24,000 crore across two tranches. The scheme prescribes a milestone-linked disbursement calendar tied to each Letter of Award — pilot line commissioning typically within 24 months of LoA date, partial commercial capacity ramp through Year 2 and Year 3, full commercial capacity by Year 4 or Year 5. Each milestone tranche is disbursed only after certification of capex incurred, OEM equipment installation, technology partner process readiness, and BIS/IEC product-standard compliance. MNRE reserves a force-majeure review provision for schedule variance attributable to documented exceptions such as monsoon-window construction delays or supply-chain disruption on imported equipment.
  • Solar Energy Corporation of India (SECI) — Tranche-II implementation and milestone certification — SECI, the Public Sector Undertaking under MNRE, implements PLI Tranche-II Rs 19,500 crore for 39,600 MW across 11 bidders awarded April 2023. SECI's milestone certification workflow requires: (a) a SECI/IREDA-appointed chartered accountant statutory-auditor-style certification of capex incurred against the applicant's audited financial statements and equipment purchase order register; (b) OEM equipment vendor invoice with delivery challan and installation completion proof; (c) technology partner (typically the process-licensing OEM for the cell diffusion or module lamination line) certification of process readiness; (d) BIS product certification for the applicable wafer, cell, and module SKUs; (e) IEC 61215 module design qualification and type approval plus IEC 61730 module safety qualification test reports.
  • Bureau of Indian Standards — solar PV module certification IS 14286 / IS 61215 / IS 61730 — The Bureau of Indian Standards is the national standards body. IS 14286 is the Indian adoption of IEC 61215 crystalline silicon terrestrial photovoltaic modules — design qualification and type approval. IS 61730 Part 1 and Part 2 is the Indian adoption of IEC 61730 photovoltaic module safety qualification (construction requirements and testing requirements). BIS certification against these standards is a prerequisite for the module SKU to be considered eligible for PLI milestone certification and separately for inclusion in the Approved List of Modules and Manufacturers (ALCM) required for Domestic Content Requirement project supply.
  • IEC 61215 and IEC 61730 international module standards — IEC 61215-1 sets out the general requirements for crystalline silicon terrestrial photovoltaic module design qualification and type approval, covering visual inspection, maximum power determination, insulation test, temperature coefficient measurement, thermal cycling, humidity-freeze cycling, damp heat exposure, mechanical load, hail impact, and hot-spot endurance. IEC 61730-1 sets out module safety qualification construction requirements. IEC 61730-2 sets out safety qualification testing requirements including accessibility, cut susceptibility, ignitability, and reverse-current overload. A module design that fails any test protocol cannot be certified against the standard and cannot be marketed as IEC-compliant. Test reports are issued by IEC-accredited laboratories.
  • Ind AS 20 conditional-grant recognition on milestone certification — Notified by the Ministry of Corporate Affairs under the Companies (Indian Accounting Standards) Rules 2015. For a milestone-linked PLI Solar PV disbursement, recognition of the grant tranche follows each milestone certification event — the pilot commissioning milestone triggers recognition of the pilot tranche, each subsequent capacity certification triggers that year's tranche. Where a milestone slips beyond its LoA target date and attracts a penalty-schedule reduction on the per-MW indicative incentive, the recognised tranche amount is the reduced amount, not the original nominal ceiling. Where the applicant has filed a force-majeure exception request and MNRE approval is pending, the grant is not recognised until the exception is granted and the milestone stands re-baselined.

Frequently Asked Questions

What is the PLI Solar manufacturing facility commissioning milestone calendar under MNRE Tranche-II, and where do the pilot line, partial commercial, and full commercial commissioning events sit?
The MNRE PLI Solar PV Modules Tranche-II Rs 19,500 crore scheme, implemented by the Solar Energy Corporation of India (SECI) with Letters of Award issued April 2023 for 39,600 MW capacity across 11 bidders, prescribes a milestone-linked commissioning calendar over five to six years from the LoA date. The pilot line commissioning milestone is typically due within 24 months of the LoA date — for a bidder with an April 2023 LoA that lands the pilot commissioning target at April 2025 (FY 2024-25 close). Partial commercial capacity ramp is scheduled through Year 2 and Year 3 of the LoA (FY 2024-25 and FY 2025-26), and full commercial capacity is scheduled for Year 4 and Year 5 (FY 2026-27 and FY 2027-28). Each milestone triggers a disbursement tranche against the LoA ceiling, and each tranche requires a full certification pack — SECI/IREDA-appointed CA capex certification, OEM equipment invoice and installation proof, technology partner process-readiness certification, BIS product certification, and IEC 61215 and IEC 61730 module type-approval reports. The exact LoA schedule per bidder is specified in the individual Letter of Award and is not published in aggregate.
Who certifies capex incurred for milestone-based disbursement, and what does the CA certification pack contain?
SECI (for Tranche-II) or IREDA (for Tranche-I) appoints or empanels a chartered accountant to perform a statutory-auditor-style certification of capex incurred against each milestone. The CA certification pack contains: (a) reconciliation of the equipment purchase order register to the audited fixed asset register in the applicant's books, (b) tie-out of the imported equipment landed cost against the ICEGATE Bill of Entry data and IGST paid at customs, (c) confirmation of GRIR (goods received not invoiced) balances cleared at year-end, (d) capitalisation cut-off tests showing which equipment is under construction (CWIP) versus commissioned and depreciable, (e) match of contractor and civil-works billing against the site progress-billing schedule, and (f) a signed statement that the capex claimed against the milestone is verifiable to source documents and books of account. The CA certification is the primary evidence SECI relies on to unlock the milestone tranche and is materially aligned with a statutory audit fixed-asset workpaper set.
What are IEC 61215 and IEC 61730, and how do they interact with BIS certification for milestone certification?
IEC 61215 is the international standard for crystalline silicon terrestrial photovoltaic module design qualification and type approval, covering the full accelerated stress test protocol (visual inspection, insulation, thermal cycling, humidity-freeze, damp heat, mechanical load, hail impact, hot-spot). IEC 61730 is the international standard for photovoltaic module safety qualification, covering construction and testing requirements. India adopts both standards via the Bureau of Indian Standards as IS 14286 (adoption of IEC 61215) and IS 61730 Part 1 and Part 2 (adoption of IEC 61730). BIS certification against IS 14286 and IS 61730 is functionally equivalent to IEC 61215 and IEC 61730 test reports issued by an IEC-accredited laboratory. For PLI milestone certification, SECI accepts BIS certification for domestically-marketed SKUs and IEC test reports for export-marketed SKUs. A module SKU that fails any protocol test cannot be certified and cannot be counted toward the milestone commissioning capacity — the reconciliation surface is a per-SKU certification status register (test lab identity, certification date, standards version, expiry date) cross-referenced against the milestone commissioning capacity claim.
What is the MNRE force-majeure review provision, and when can a milestone slippage be exempted from the per-MW incentive penalty?
MNRE reserves a force-majeure review provision under the PLI Solar PV Modules scheme rulebook that allows an applicant to request exemption from the per-MW incentive penalty reduction for milestone slippage attributable to documented exceptions. The commonly-invoked exception heads are: monsoon-window civil-works delay affecting the greenfield plant construction schedule, supply-chain disruption on imported equipment (specifically the diffusion furnaces, wire saws, and lamination lines that are typically imported from a small set of specialised OEMs), and technology-transfer delays from the process-licensing partner. The exception request must be filed with documentary evidence — meteorological data for monsoon delays, shipping data and OEM correspondence for supply chain, and technology partner correspondence for transfer delays. MNRE reviews the request and either grants a re-baselining of the milestone date without penalty, or denies the request and confirms the penalty-schedule reduction on the applicable milestone tranche. The reconciliation surface is a force-majeure claim register (event date, exception head, documentary evidence pack, MNRE decision, re-baselined milestone date if granted) that runs parallel to the milestone calendar tracker.
How is a milestone slippage penalty computed, and how does it flow through the Ind AS 20 recognition entry?
The penalty schedule for milestone slippage is specified in each Letter of Award and typically operates as a percentage reduction in the per-MW indicative incentive for each month (or fraction of a month) of slippage beyond the LoA target date, applied to the commissioned capacity portion actually attributable to the delayed milestone. For an illustrative Tranche-II bidder holding a 2,400 MW LoA with a pilot commissioning target of 120 MW by April 2025, an actual pilot commissioning of 100 MW in May 2025 (one month slippage) at an illustrative per-kW incentive of Rs 5,500 attracts a 0.5 percent reduction on the pilot tranche — approximately Rs 27 lakh reduction on that 100 MW pilot portion. The reduced tranche amount flows through the Ind AS 20 recognition entry as the amount actually receivable, not the original nominal ceiling, and the corresponding Section 115JB MAT book-profit adjustment reflects the reduced amount. Where a force-majeure exception request is filed and pending MNRE decision, the applicant does not recognise the grant tranche until the exception is granted (re-baselined milestone with no penalty) or denied (recognise the reduced amount). Recognising the nominal ceiling before the exception decision creates a prior-period recognition adjustment risk if the decision comes back with a penalty.

See how TransactIG handles reconciliation for your industry

Configuration takes 2–4 weeks. No code development required. ISO 27001:2022 certified.